One of the most important jobs on the very long list we made when we took over the marina was refurbishing the bridge to the island. A general lack of maintenance over the years since it was first built in the early ‘90s had been further compounded by mild damage suffered when a boat underneath it caught fire!
So, as well as giving it a much-needed aesthetic facelift, we wanted to make sure the whole bridge structure was fully compliant with current Health & Safety standards and providing proper services to the island moorings.
Over a period of two weeks, we reinforced the structure, painted it, replaced all the stair treads and walkway deck with an anti-slip surface and put up safety guards. We also had a cable tray fitted to support the new insulated water pipe and mains electricity cable.
And we’re very pleased with it. The only downside, as our son pointed out, is that he can no longer play ‘Pooh sticks’ from the top. More outings to Halfpenny Bridge have been promised!